Assemble the buttresses

Updated: Sep 3, 2022

31st August 2022

On top of the bottom wall elements, there are the buttresses. We assembled half of them this week. It is similar procedure as bottom wall like leveling the platform, putting beams and connectors and spacers, cramping, screwing, but the buttress has much longer connectors and beams in upper part. The most difficult thing here was to put the 8-10m long beams on top by crane. They are very heavy element, so we tried best to align them with teamwork💪 We also prepared for delivering by making the small platforms, putting the straps, fixing the bracing. We happened to see the sunset at Paja🌇